one mega watt power plant investment idea
1. space requirement -five acres land. Preferred near to sub-station (11kv-33kv)
2. estimated cost - 6.8 cr's tentative.
3. break even period - tentative 6 years time frame. Rec scheme & ppa cost play major impact on bep.
4. bank fund or loan - we can show the path & refer to the bank but maximum of loan depends on
credibility & against collateral.
5. time of installation - minimum 4 months & maximum 6 moths depending on client fund release & clearance.
6.government benefits - 1. Tax exemption on land registration 2. Tax waiver on imports 3. No transmission & wheeling charges ....
7. advantage - proper ppa & epc contract will fetch good return in the future
1. space requirement -five acres land. Preferred near to sub-station (11kv-33kv)
2. estimated cost - 6.8 cr's tentative.
3. break even period - tentative 6 years time frame. Rec scheme & ppa cost play major impact on bep.
4. bank fund or loan - we can show the path & refer to the bank but maximum of loan depends on
credibility & against collateral.
5. time of installation - minimum 4 months & maximum 6 moths depending on client fund release & clearance.
6.government benefits - 1. Tax exemption on land registration 2. Tax waiver on imports 3. No transmission & wheeling charges ....
7. advantage - proper ppa & epc contract will fetch good return in the future